• CLF asks PSB for pipeline permit change
    Staff Report | July 14,2014
    • Email Article
    •  
    •  Print Article
     
    MONTPELIER - The Conservation Law Foundation asked the Public Service Board on Monday to require Vermont Gas Systems to seek an amended certificate of public good for Phase I of its natural gas pipeline project.

    In its filing, CLF cited a $35 million, or 40 percent, increase in the cost of the project. CLF also asked the board to require VGS to halt construction unless and until it receives an amended permit.

    "Vermont Gas is obligated to seek approval for any substantial change to its project. A 40 percent cost increase is a substantial change that requires review," Sandra Levine, CLF senior attorney said in a statement.

    Vermont Gas received PSB approval in December for Phase I of its Addison Rutland Natural Gas Project. Phase I would extend the pipeline from Chittenden to parts of Addison County, including Middlebury.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    PARIS — You can’t put a guard in every church and patrol every beach. Full Story
    A New Hampshire man has been arrested for possession of heroin following a traffic stop on I-91... Full Story
    GROTON — State police have arrested a Groton man for a drug-related death that occurred at his... Full Story
    More Articles