• CLF asks PSB for pipeline permit change
    Staff Report | July 14,2014
    • Email Article
    •  
    •  Print Article
     
    MONTPELIER - The Conservation Law Foundation asked the Public Service Board on Monday to require Vermont Gas Systems to seek an amended certificate of public good for Phase I of its natural gas pipeline project.

    In its filing, CLF cited a $35 million, or 40 percent, increase in the cost of the project. CLF also asked the board to require VGS to halt construction unless and until it receives an amended permit.

    "Vermont Gas is obligated to seek approval for any substantial change to its project. A 40 percent cost increase is a substantial change that requires review," Sandra Levine, CLF senior attorney said in a statement.

    Vermont Gas received PSB approval in December for Phase I of its Addison Rutland Natural Gas Project. Phase I would extend the pipeline from Chittenden to parts of Addison County, including Middlebury.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    NEW YORK ó His defiant protests helped shape Americansí opposition to the Vietnam War. Full Story
    Activist, Jesuit priest Daniel Berrigan dies at 94
    When Rutland City Mayor Christopher Louras told those gathered in the cityís aldermanic chambers... Full Story
    Immigrants part of Rutlandís fabric
    Sascha Mayer, co-founder and CEO of the Vermont-based company Mamava, has been... Full Story
    Vermonter to meet NYT journalist who inspired her company
    More Articles